Hidroinjekt Ltd. performed the emergency strengthening of the compromised retaining wall on the road II-51 Byala – Popovo from km 0 + 858 to km 0 + 908 in the town of Byala. The construction activities were financed with budget funds under the Emergency Program for 2017 of the Road Infrastructure Agency. A power fortification structure with a length of 30 m has been made, 30 pieces have been made to strengthen the existing retaining wall. Micropiles with a length of 12 m and 58 pcs. anchors with a length of 24 m. A new road surface has been laid in the section of the facility and a new horizontal marking.

The construction and installation works performed by Hidroinjekt Ltd are worth BGN 470,191.35 with VAT.

Emergency strengthening of a retaining wall

The intense rains at the end of 2014 caused significant damage to the retaining wall of the second-class road passing through the town of Byala. The retaining wall limits the bed of the Belenska River and is part of the construction of the sidewalk on Stefan Stambolov Street in the city. Prior to the repair of the retaining wall, the speed of movement through the section was limited to 30 km / h. and the passage of vehicles over 10 tons was prohibited.